Bali Toll Road Due to Open in April

Progress Report from PT Waskita Karya on Benoa - Ngurah Rai Nusa Dua Toll Road in Bali

(11/24/2012) PT Waskita Karya, the state-owned construction company, has announced that they are optimistic that the Benoa – Ngurah Rai Airport – Nusa Dua toll road will be completed on time.

The Rp. 773 billion (US$80.5 million) project will be completed in April 2013.

Waskita Karya is entrusted with completing packet 2 and packet 4 of the 4-part project.

Quoted by the State News Agency Antara, the director of Waskita Karya, M. Choliq said that 50% of packet two and 78% of packet four are now completed.

Separately the Minister of State-owned Enterprises, Dahlan Iskan has expressed his deep satisfaction with the construction of Bali’s first toll way.

“I am satisfied with the optimal synergy which has been given in he process of building this toll road; I hope that in the future the Nusa Dua-Ngurah Rai – Benoa toll road will help overcome traffic congestion in Bali,” said Dahlan.

M Choliq said the two packets of construction undertaken by PT Wastika Karya were packet two located near Benoa and traveled over the shallow sea using 3,028 foundation pillars over a distance of 2.4 kilometers and packet four using 3,641 foundation pillars over a distance of 2.2 kilometers.

The new toll way, together with the renovation of Bali’s airport and a new underpass at Simpang Siur, are all being targeted to be in place and fully operation before the APEC conference planned for Bali in late 2013.